Jewelry OEM Sampling: The CAD to Production Timeline
A realistic week-by-week timeline from a sketch or reference photo to bulk production, including what causes the delays, how many revision rounds to budget for, and how to approve a sample properly.
Custom jewellery development fails on timelines more often than on quality. Buyers budget two weeks for sampling because that is what a supplier promised, then lose a season when it takes five. This is the sequence with realistic durations, and the points where schedules actually slip.
The full sequence with realistic durations
| Stage | Duration | What you receive | Common delay cause |
|---|---|---|---|
| Brief and feasibility | 1 to 2 days | Feasibility note, stone options, indicative price | Vague reference images |
| Quotation | 2 to 3 days | Costed quote with stone, metal, labour and mould broken out | Specification changes mid-quote |
| CAD and 3D render | 3 to 5 days | Render from three angles plus top view | Buyer requests many small changes |
| Revision rounds | 2 to 3 days each | Updated render | Underestimating rounds needed; budget two |
| Mould and wax | 3 to 5 days | Wax photograph before casting | Design complexity |
| Cast, set and polish sample | 5 to 8 days | Physical sample with stone set | Stone sourcing for unusual sizes |
| Sample shipment | 3 to 7 days | Insured express parcel | Customs documentation |
| Sample approval | 1 to 3 days | Signed approval sheet | Buyer-side decision time |
| Bulk production | 12 to 20 days | Production run | Queue position behind larger clients |
| QC and certification | 3 to 5 days | QC report, certificates | Third-party grading turnaround |
| Packing and dispatch | 2 to 3 days | Carton photographs, documents | Custom packaging printing run |
Realistic total: six to nine weeks from brief to goods in hand for a new design. If you are launching for a season, start twelve weeks out. A supplier promising three weeks is describing stock adaptation, not a new mould.
Writing a brief that does not require three revisions
- Give dimensions, not adjectives. A 7 mm wide band, 2.2 mm thick, with a 1.0 ct centre, rather than chunky but elegant.
- Give a reference with a purpose. Say what you like about it: the prong style from image A, the shank profile from image B.
- State the stone and grade up front. Changing stone size after CAD invalidates the render.
- State the metal and target weight. Metal weight drives both cost and how the piece feels in the hand.
- State your retail price point. It lets the factory propose a workable specification rather than quoting something unsellable.
- Send vector or high-resolution source files for any logo or engraving.
Budget for two revision rounds
| Round | Typical change | Cost implication |
|---|---|---|
| Round 1 | Proportions, prong style, shank thickness | Usually free, because CAD is parametric at this stage |
| Round 2 | Stone size, setting height, gallery detail | Sometimes free; may require a new mould drawing |
| Round 3 and beyond | Fundamental redesign | Normally charged as a new development |
Ask at the quotation stage how many revision rounds are included. Two is a fair standard. Unlimited revisions usually means the cost is hidden elsewhere.
Approving a sample properly
| Check on the sample | Acceptance criterion |
|---|---|
| Stone grade and size | Matches the specification sheet; request the certificate with the sample |
| Prong security and symmetry | No gap, no rocking, gaps equal within 0.2 mm |
| Weight | Within plus or minus 5% of the agreed target weight |
| Dimensions | Band width and thickness within 0.2 mm |
| Plating and finish | Even colour, no edge thinning, mirror polish inside the shank |
| Comfort | No sharp edge on the inner band; the piece sits level on the finger |
| Setting height | Matches the render; not raised or lowered without agreement |
Approve in writing against the specification sheet, and attach photographs of the approved sample. That sample becomes the master reference for the bulk run, which is the single most useful document in the whole order, because it converts it looks different into a measurable comparison.
Where suppliers and buyers actually lose time
- Buyer-side decision latency. The most common cause by far. Every day you sit on a render adds a day to delivery.
- Stone sourcing for non-standard sizes. A 1.35 ct pear is not a stock size. Add five to eight days if your specification is unusual.
- Custom packaging. Printed boxes and care cards have their own production lead time of 10 to 15 days. Order them in parallel, not after approval.
- Third-party grading. IGI grading adds turnaround outside the factory control. Certify a subset rather than the whole run if the deadline is tight.
- Change orders after production starts. Acceptance of a mid-run change resets the schedule and is correctly charged.
Running development in parallel with sales
| Week | Development activity | Commercial activity |
|---|---|---|
| 1 to 2 | Brief, quote, CAD | Pre-sell the render to gauge demand |
| 3 to 4 | Revisions, mould, sample | Prepare listing copy and sizing content |
| 5 to 6 | Sample in hand, approved | Shoot the physical sample; open pre-orders |
| 7 to 9 | Bulk production | Finalise packaging and launch assets |
| 10 to 12 | QC, packing, shipping | Schedule the launch for arrival week |
Buyers who run development and commercial preparation in parallel launch within days of arrival. Buyers who do them sequentially lose two to three weeks of selling time on every new design, which across a season is the real cost of OEM development.
Related Articles
- How to Buy Lab Grown Diamonds Wholesale: A 2025 Importer’s Guide
- Wedding Ring Wholesale Buying Guide for Retailers and Brands
Authoritative References
For buyers who need to verify the technical and regulatory basis of this guide, the following independent institutions publish authoritative reference data:
- ISO 9001 Quality Management - the international standard for consistent production quality.
- Wikipedia: Jewellery - manufacturing processes, materials and global trade background.